The No. 2 software park in Da Nang took shape after 5 months of construction


Software Park No. 2 (Phase 1) uses the City budget, with a total investment of nearly 704 billion VND with a construction time of 690 days. The project is located on a construction site with a total area of 28,573m2, in Thuan Phuoc ward, Hai Chau district.


The work consists of a 20-storey ICT office building block with a total floor area of 26,267m2; 8-storey office building block ICT1 8-storey with a total construction floor area of 39,297m2; The office building block combines the 8-storey ICT2 coffee area with a total construction floor area of 27,220m2 with a system of yards, internal traffic, green landscape, grass, and synchronous technical infrastructure system. (ground leveling, traffic, water supply and drainage, lighting electricity, ...).


After completing the project, it is expected to meet about 6,000 jobs directly in information technology and digital technology.